The system comprises a total of 2 belt conveyors with a combined conveying length of 2500m. Two tensioning methods are adopted: gravity take-up and trolley take-up. The configuration includes one pipe belt conveyor with a pipe diameter of 400mm, a conveying capacity of 750t/h, and a belt speed of 2.8m/s, as well as one belt conveyor with a belt width of 1000 mm, a conveying capacity of 750 t/h, and a belt speed of 2.5 m/s. The system is equipped with a fully enclosed guide chute, a spray dust-suppression system, and a bag-type dust-collection system.

The system consists of a single pipe belt conveyor with a pipe diameter of 400 mm, a total length of 1530m, a conveying capacity of 1100 t/h, and a belt speed of 3.5 m/s.

The project includes a total of 6 conveyors, consisting of 4 pipe belt conveyors, 1 stacker-reclaimer, and 1 ship loader.